Labs and lab equipment

The complete lab relocation guide

A lab move is a project, not just a move. Planned properly, the lab is back at work quickly with no damage to equipment or samples. Here are all the stages, in order.

Who this guide is for

This guide is for lab managers, safety officers and operations managers planning a lab move: to a new building, another floor or another room on the same campus. It covers every stage, from planning until the lab is working again, and ends with a downloadable checklist.

Timeline: 8 weeks before

  • Appoint a move coordinator from the lab
  • List equipment by room, with dimensions and weight for large items
  • Check the new lab: power, gases, drainage, air conditioning and space for each instrument
  • Ask the instrument manufacturers and technicians what disconnection and reconnection require
  • Request a moving quote

Timeline: 4 weeks before

  • Draw a layout of the new lab with a place for every instrument and piece of furniture
  • Set a date with the movers, the technicians and both buildings' management
  • Book a certified tester for fume hoods and safety cabinets for the day after placement
  • Decide what isn't moving: old equipment, furniture and expired materials

Timeline: 2 weeks before

  • Plan the sample transfer and a backup freezer
  • Arrange elevators, parking and unloading hours at both buildings
  • Receive packing materials and start packing equipment not in use
  • Update suppliers and couriers with the new address

Timeline: 1 week before

  • Remove chemical and biological materials and pack them per lab procedures
  • Clean and decontaminate fume hoods, safety cabinets, incubators and fridges
  • Photograph instrument connections before disconnecting
  • Label every box and instrument with a number and destination room

Timeline: The day before

  • Technicians disconnect instruments and lock moving parts
  • Defrost and dry fridges and freezers that move empty
  • Back up data from instrument computers
  • Confirm the new lab is open, clean and ready

Timeline: Moving day

  • The coordinator is at both ends, with the layout
  • Freezers, hoods and sensitive equipment first, then furniture and boxes
  • Every item is placed in its marked room and spot
  • Check that every box arrived against the list

Timeline: After the move

  • Freezers and fridges stand before switching on, per the manufacturer
  • A certified tester certifies fume hoods and biosafety cabinets
  • Technicians connect, calibrate and test instruments
  • Samples go back only after the freezer reaches temperature

Who is responsible for what

A lab move succeeds when it is clear in advance who does what.

  • The lab: chemical and biological materials, cleaning and decontamination, samples and documentation
  • Technicians and manufacturers: disconnecting, connecting, calibrating and testing instruments
  • The movers: packing, moving, placement and coordination on moving day
  • Building management: freight elevators, parking, working hours and entry approvals

Freezers and samples

A −80 freezer moves empty, upright and strapped. Samples move separately, on dry ice or in a backup freezer. The order is planned so that never too many freezers are off at the same time.

Fume hoods and biosafety cabinets

Hoods travel upright, wrapped and secured. After every move they need testing and certification by a certified tester, so book one in advance.

Analytical instruments and microscopes

Moving parts are locked per the manufacturer's instructions, packed with padding and moved in an enclosed truck. Shock-sensitive equipment travels strapped and is never stacked.

Furniture, cabinets and computers

Lab benches and cabinets are dismantled and reassembled according to the layout. Computers and screens are packed separately, with cables in a bag labeled with the workstation.

What affects the price

  • Number of rooms and instruments
  • Especially heavy or tall equipment
  • Access: elevators, stairs and parking distance
  • Working hours: evening or weekend
  • Distance between the two sites

Lab relocation checklist (PDF)

Every step from this guide in one printable list, with boxes to tick off.

Download the checklist

Detailed guides for each topic

  • Lab relocation checklist: A clear lab relocation checklist: equipment list, owners, disconnecting systems, moving samples, packing, moving day and post-move checks.
  • How much does a lab move cost?: What makes up the price of a lab move: amount of equipment, sensitive instruments, fume hoods and freezers, distance, access and work hours. And how to get an accurate quote.
  • Moving a −80 freezer: How to move a −80 freezer without risking samples: a sample plan, dry ice, a backup freezer, upright transport and a wait before switching on.
  • Moving a CO2 incubator: How to move a CO2 incubator: emptying and cleaning, disconnecting gas, upright secured transport, and stabilizing before cultures return.
  • How to move a chemical fume hood safely: A practical guide to moving a chemical fume hood: cleaning and disconnection, measuring the route, dismantling per the manufacturer, wrapping, upright transport and placement.
  • Biosafety cabinet moving: How a biosafety cabinet is moved: decontamination before the move, upright packing, measuring the route, placement and recertification after relocation.
  • Biosafety cabinet after a move: Why a biosafety cabinet needs testing and recertification after every move, what it includes, and how to fit it into the move plan.
  • Moving analytical instruments: How to move HPLC, GC, mass spectrometers and other analytical instruments: technician preparation, padded packing, secured transport and start-up at the new site.
  • Moving an electron microscope: What to know before moving an electron microscope: manufacturer preparation, weight, shock sensitivity, new room conditions and reinstallation.
  • Moving lab furniture: How lab furniture is moved: workbenches with heavy tops, chemical cabinets, ventilated cabinets and shelving. Dismantling, labeling and reassembly at the new site.
  • Moving a lab within the same building or campus: How to move a lab between floors, rooms or campus buildings: freight elevators, dollies, work hours, and what differs from an intercity move.
  • Hospital lab relocation: How to move a hospital lab when service must continue: phased moves, night work, hospital corridors and elevators, and staff coordination.
  • Moving sensitive equipment: What counts as sensitive equipment and how it is moved: lab instruments, test equipment, medical devices and computers. Dedicated packing, correct strapping and coordination with technicians.

About the service: Lab moving · All business moving

FAQ

How long does a lab move take?

A small lab usually moves in one day. A large lab moves over several days or in phases, room by room.

Do you move chemicals?

The lab removes and packs the materials themselves per its procedures. We move the equipment, furniture and instruments.

Who connects the instruments at the new site?

The lab's or manufacturer's technicians. We coordinate the hours with them.

Can a lab move without stopping work?

Yes. We move in phases or at the weekend, so most of the lab keeps working.

How do we get a quote?

Send an equipment list, photos or a video and both addresses on WhatsApp.