Factory relocation timeline

A plant that moves without a timeline discovers problems on the last day. Here's a work order that starts three months ahead.

Three months before

  • Set up a move team and a lead
  • Map lines, storage and offices, and coordinate machine moves with the manufacturers
  • Check the new building: power, floor, doors, ramps
  • Get quotes

One month before

  • Finalize a phased plan
  • Book manufacturers' technicians
  • Notify customers and suppliers
  • Prepare a location layout of the new building

Move week

  • Build up stock in advance to cover the days
  • Move storage and offices first
  • Move lines one after another

Start-up day

Start the first line, test, and only then continue. Finally remove packing and leave the old building tidy.

About the service: Warehouse and plant relocation · All business moving

FAQ

How long does a factory relocation take?

Depending on size, from a few days to several weeks in phases.

What moves first?

Usually storage and offices, then production lines.

How to shorten downtime?

Stock built up in advance and a phased move.